Crosby Garage 59 Partridge Trail Leicester, Vermont
The Site Work April 26, 2017
Edward Davis our Grandson enjoys climbing on the excavator.
The Garage floor forms May 10, 2017
Jim Ploof from Ploof's Excavating preparing the site work for the garage floor. The garage will be 28' x 32' with log siding.
May 10, 2017
In the pictures above the site work is completed and the cement forms are prepared for the garage floor. The cement will be poured on the next warm dry day.
The Floor Completed
May 16, 2017
We finally have a cement floor for the garage. It's been a long process getting to this point with all the problems from the State of Vermont Shore land permitting system.
Framing has Started
May 24, 2017As you can see the walls for the garage are starting to go u. Rayce and his crew are coming along with the first wall. In this picture the back wall is just about to go up.







Comments
Post a Comment