Crosby Garage 59 Partridge Trail Leicester, Vermont

The Site Work  April 26, 2017


 
     Edward Davis our Grandson enjoys climbing on the excavator.

 The Garage floor forms May 10, 2017


  Jim Ploof from Ploof's Excavating preparing the site work for the garage floor.  The garage will be 28' x 32' with log siding.


May 10, 2017

In the pictures above the site work is completed and the cement forms are prepared for the garage floor.  The cement will be poured on the next warm dry day.

 The Floor Completed


May 16, 2017

We finally have a cement floor for the garage.  It's been a long process getting to this point with all the problems from the State of Vermont Shore land permitting system.









 Framing has Started

May 24, 2017
 As you can see the walls for the garage are starting to go u.  Rayce and his crew are coming along with the first wall.  In this picture the back wall is just about to go up.